The typical lead time for custom titanium alloy forgings (such as Ti-6Al-4V) generally ranges from 4 to 14 weeks after the receipt of the order (ARO), depending heavily on the project's complexity and the current availability of the raw material [1].
For standard titanium forged rings or simple shapes, the lead time is often shorter, typically 4 to 6 weeks. However, complex, large-scale, or aerospace-grade forgings requiring specialized testing and heat treatment can extend the schedule to 10 weeks or more [2].

Titanium forging is a complex, multi-stage process involving raw material sourcing, forging, heat treatment, and quality inspection. Several factors directly impact the final delivery schedule:
| Factor | Impact on Lead Time | Mitigation Strategy |
|---|---|---|
| Raw Material Availability | If the required alloy (e.g., Ti-6Al-4V ELI) is not in stock, the lead time for melting and billet preparation can add 4-8 weeks. | Work with manufacturers who maintain a large inventory of common titanium billets. |
| Forging Complexity & Size | Large, intricate shapes (e.g., turbine discs) require multiple forging steps and specialized dies, significantly increasing the time required. | Simplify design where possible; utilize near-net-shape forging to reduce subsequent machining time. |
| Heat Treatment & Testing | Aerospace and medical forgings require mandatory, time-consuming processes like solution treatment, aging, and extensive Non-Destructive Testing (NDT). | Ensure the supplier has in-house heat treatment and testing facilities to avoid external delays. |
| Order Volume & Backlog | High-volume orders or a manufacturer's existing production backlog can delay the start of your project. | Confirm the manufacturer's current capacity and production schedule before placing the order. |
A typical custom titanium forging project follows this timeline:
Quotation & Order Confirmation: 1-3 days.
Raw Material Sourcing/Preparation: 1-8 weeks (depending on stock).
Forging (Hot Working): 1-2 weeks (multiple steps required).
Heat Treatment (Annealing/Aging): 1-2 weeks.
Inspection & Testing (NDT, Mechanical): 1-2 weeks.
Final Machining & Shipping: 1 week.
We understand that project timelines are critical. Our factory utilizes streamlined production processes and maintains a large inventory of common titanium alloy billets (including Ti-6Al-4V) to offer some of the industry's fastest lead times for custom forgings. We specialize in near-net-shape forging to reduce your machining costs and delivery schedule.